Secretary of the Provincial Party Committee Chau Van Lam inspected the construction progress of Tuyen Quang - Phu Tho expressway connecting with Noi Bai - Lao Cai highway.
Secretary of the Provincial Party Committee Chau Van Lam suggested that the Provincial Traffic Construction Investment Project Management Board continue to closely coordinate with local authorities and functional agencies of Phu Tho province to complete the project, focusing on compensation and site clearance as well as the quality the expressway.
He noted that the Management Board should soon have a solution to prepare the embankment land for the construction of Tuyen Quang - Ha Giang expressway in the near future, ensuring on schedule, quality, and connecting key economic regions in order to well implement the goal of turning Tuyen Quang into a fairly, comprehensively and sustainably developed province.
Tuyen Quang - Phu Tho highway project is divided into 30 bidding packages, of which there are 8 construction and installation packages. 29 out of 30 bidding packages have been completed, and 1 bidding package will be held in the first quarter of 2023 in accordance with the approved bidding plan.
The construction and installation bidding packages have been implemented since the beginning of August, 2021, both construction and site clearance. Construction progress meets the scope of the handover site; The volume of construction and installation so far has reached VND994.35 million out of VND1.829.59 billion, reaching 54.35% of the contract value.